EngineeringEnvironmental Science

U. Shamir, C. D. Howard

1979.5.1Journal AWWA

DOI: 10.1002/j.1551-8833.1979.tb04345.x

Abstract

A procedure is described that uses the history of main breaks to forecast how the number of breaks would change with time if the pipe were not replaced; a separate analysis predicts the failure rate of newly installed pipes. These forecasts are combined with cost data and a discount rate that accounts for inflation to determine the optimal replacement date.

Citation format

SHAMIR, U.; HOWARD, C. D. An analytic approach to scheduling pipe replacement. Journal AWWA, 1979, 71: 248–258.